The Transportation Enhancement Project will begin on Pioneer Street.  Mobilization will begin Tuesday, September 4, with construction beginning on September 10.  Please contact the Village Office at 547-2411 with any questions regarding the project.  To view or download the power point from the August 29, 2018 public information meeting providing project details click on this PDF – TEP Public Information Meeting Presentation PP

Proposed Schedule –  Week of 10/22 – 11/15

 

  1. Finish preparing Sidewalk areas on North Pioneer Street for concrete placement ( complete week of 10/15) with the exception of Sidewalks by Businesses

 

  1. Begin Excavation for the retaining wall at the Park, North east corner Pioneer St. at Main.

 

  1. Installation of Light Pole Bases beginning in the North Corridor of Pioneer Street. ( Possible start Oct. 24)

 

  1. Move to the South Corridor and continue with installing Light Pole Bases.

 

  1. Begin Sidewalk replacement Nov. 5th .

 

All Dates tentative based on weather conditions.

 