Below is work anticipated for the remainder of the spring 2019 portion of the project, to be completed no later than mid-day May 24.

  • Pioneer- Reconstruction of lawns and driveways
  • Tree installs on Pioneer
  • Sidewalk removals Hoffman lane to Fair
  • Lightpole Bases and conduit installs Hoffman to Fair
  • Concrete Pour Hoffman to Fair
  • Light Pole Base and conduit from Fair to River
  • Paver Install Fair to River
  • All benches to be installed
  • Reinstall Parking Kiosks 

  Additionally there is a project update meeting scheduled for this Wednesday, April 10 at 6 p.m. in the Ballroom of Village Hall, 22 Main Street.  Following the project update for the above project, information will be provided regarding the Doubleday Field Project, particularly the first phase of the project, the 3rd base bleacher demolition.   Teri